SAFEBUCK Phase II: Workscope
There are four key elements within the proposed scope of work:-
- Task 1: Pipeline Response Modelling (Lead Boreas);
- Task 2: Definition of Limit States (Lead Boreas/ TWI);
- Task 3: Pipe-Soil Interaction Testing (Lead Cambridge University);
- Task 4: Production of Guideline (Lead Boreas).
Within the JIP team, the company with lead responsibility for each activity is outlined above, however other members within the team will undertake checking and validation functions.
The details work scope is split into these four tasks and subdivided by activity as summarised in the table below.
| Section |
Description |
3.1.1
3.1.2
3.2.1
3.2.2
3.3.1
3.3.2
3.4.1
3.4.2 |
Task 1a Structural Reliability Modelling
Task 1b Dynamic Modelling of Lateral Buckling
Task 2a Local Buckling Limit State (Analysis and Testing)
Task 2b Fatigue Limit State
Task 3a Lateral Pipe-Soil Interaction, Mini-Drum Experiments
Task 3b Pipeline Walking
Task 4a Independent Review of Lateral Buckling Design Guidelines
Task 4b Guideline Update |
|